Aircraft Maintenance Cost Prediction
✅ Paper Type: Free Essay | ✅ Subject: Engineering |
✅ Wordcount: 3734 words | ✅ Published: 1st Jan 2015 |
Aircraft-commerce, Aircraft Operator and owner's guide, [issue 66, October 2009] states Canadair Regional Jet-200 are nominally 50-seat, five-crewmember, twin- turbofan-powered aircraft with a maximum altitude of 41,000ft and a maximum design airspeed of Mach 0.85. The only difference between them is that the CRJ-200 has a later engine, the CF34- 3B1. The cabin is 8.43 feet (2.53m) wide with four-abreast seating, 50 seats at 31- inch pitch as standard, and checked baggage capacity of 3,500lbs (308 cubic feet). The CRJ-200 similarly had ER and LR versions; it ranges of 1,229nm and 1,585nm.. In all cases, maximum zero-fuel weight (MZFW) is 44,000lbs, maximum payload weight is 13,000lbs and maximum take-off weight (MTOW) is 53,000lbs.
The CRJ-100 programme was launched in March 1989, and the first aircraft was delivered to Lufthansa CityLine in October 1992. The first flight of the CRJ-200, which was essentially a CRJ-100 with updated GE CF34 engines, took place on 13th November 1995.
Bombardier website, states that "The Bombardier CRJ200 has been designed to provide superior performance and operating efficiencies in the fast-growing regional airline industry. Against the closest competition it flies faster and farther while burning less fuel and having lower operating costs. With over 1,000 units in commercial service it has become the most successful regional airliner program the world has ever known."
Airlines Using CRJ 200
Bombardier website, states that "There are nearly 1,200 CRJ aircraft in operation in North America, which has a small number of large fleets. Europe is the second largest operator with 239 aircraft."
Following table shows top ten CRJ200 (by numbers) using airlines worldwide.
S.no
Airlines
Numbers Deployed
1
Northwest Airlines
142
2
Comair
110
3
Skywest Airlines
110
4
Delta Connection
94
5
Independence
87
6
Air Wisconsin
64
7
Lufthansa Regional
57
8
Air Nostrum
50
9
ASA
45
10
Air Canada Jazz
41
CRJ-200 Maintenance Programme:
Aircraft-commerce online magazine provide detailed information on The CRJ-200 complex airframe maintenance programme. Maintenance & Engineering, Issue 52, pg. 52, 54 [June/July 2007] points that maintenance programme has been divided into three sections:
Line and light maintenance
A checks
Base checks
These sections have different basic interval. This makes check planning complex, with the result that tasks are performed early and checks are uneven in size.
Sections are further divided into subgroups
Line and light maintenance:
There are no actual line and light checks specified in the MR, although many operators decide to add pre-flight and daily checks into their maintenance programme. The smallest check in the programme is a service check, with an interval of three days. The next largest is a 'routine' check every 100FH (Flying Hours)
Get Help With Your Essay
If you need assistance with writing your essay, our professional essay writing service is here to help!
Find out more about our Essay Writing Service
A check tasks:
Originally A check tasks were designed for interval of 400 FH but raised to 500 FH after April 2007. There are five multiples of the basic A checks; 1A to be performed every 500 FH. 2A items every 1000 FH; 3A tasks every 1500 FH; 4A tasks every 2,000 FH and 5A tasks every 2500 FH. First largest A check task is A4 which requires 95 MH (Man Hours) 1A and 3A both require 50 MH to complete and 2A and 5A both require 80 MH.
There are some other small checks, of items such as the Auxiliary Power Units (APU), these have repetitive interval of 300FH, 750 FH,1200 FH, 1500 FH, 1800 FH and 3000 FH and all use 2MH for the routine tasks. (See Annexure table 1)
C Check Tasks:
There are three groups of C checks having different interval phases.
The first of these are the main C check inspections which have intervals that are multiple of 5000 FH and it requires 210 MH. 2C tasks have 10000 FH intervals and they use 280 MH
The second group of C check tasks are Out Of Phase (OOP) items with FH intervals that are mainly multiples of 4,000FH. There are six groups, many of the tasks in which are structural inspections. The first group comes due every 3,000FH, but only uses about 1MH. This group is small, and is often added to the A checks. The second group is one of the largest, using about 70MH, and comes due every 4,000FH. The third group comes due every 8,000FH, and uses about 40MH.
The third main group of inspections has calendar intervals that are mainly multiple of one year, and there are 11 different groups of inspection tasks. The 12-month tasks consume about 20MH. This is a relatively small labor requirement. The tasks also have easy access, so they are often included in the A checks. The tasks that come due every 18 months only require about 1MH. Like the 12-month tasks, these have easy access and are often included in the A checks. The 36-month tasks only use about 7MH, require easy access, and are often included in the A checks. The remaining seven groups of inspections come due every four, five, six, eight, ten, twelve and fifteen years. The largest are the four-year, six-year and eight-year groups, each of which uses 240MH, 890MH and 780MH for routine inspections. (see Annexure table 2)
Vertical Integration of Airframe maintenance activity:
Every plane and jetliner have their own schedule of maintenance activity however various airlines try to integrate maintenance program so that maintenance cost can be reduced. At Lufthansa, www.Lufthansa-technik.com/applications/portal, In focus: Aircraft maintenance, 29.03.2011 stated that it starts with Trip check: before every take off pilot and co-pilot take a look at the plane followed by D-check under which whole plane is taken apart completely and undergoes an extensive maintenance program such checks are for every plane.
Considering only CRJ-200 jetliners grouping the three sets of inspection tasks for the A and base checks into check packages is complicated by the large number of OOP and calendar tasks with intervals that are not in phase with the FH inspections. How tasks are grouped and formed into checks depends on rates of aircraft utilization. This analysis assumes aircraft operating at 2,300-2,400FH and 2,100FC per year. Aircraft-Commerce, Maintenance & Engineering, Issue 52, pg. 52, 54 [June/July 2007] states that if we proceed with checks as they are due aircraft will be always in hangar rather than flying therefore it becomes essential to club checks so that excess maintenance should not be an issue. As base checks are most time consuming activities it is better to plan those task before all other. Aircraft with annual utilizations of about 2,000FH can have checks in phases of 24 months. This means that tasks with multiples of 4,000FH and calendar items with interval multiples of 12 and 24 months and higher can be grouped together. Tasks with intervals that are multiples of 5,000FH would have to be brought forward and performed early. In the cases where they come due at the same time as large groups of other tasks they are included in base checks. Examples are the 24-month, 48-month and 72-month checks. During five year period, it will leave task group with interval of 48 & 60 month. These are scheduled in the base checks.
Not all these tasks are able to use their full intervals, however. For example small checks at 60 month interval are brought forward to 48 month check. The second group of tasks includes those with interval multiples of 4,000FH. The first group of tasks (Group 1), with intervals of 3,000FH, only requires 1MH and can be scheduled in A checks. These tasks can also be scheduled into base checks when their interval coincides with a base check. The second and third groups (Group 2 and Group 3), which come due every 4,000FH and 8,000FH can be included in base checks. The third main group of tasks includes those with interval multiples of 5,000FH. The 1C, 2C and 3C tasks have to be brought forward in multiples of 4,000FH, 8,000FH and 12,000FH. Once these three groups of tasks are grouped together, there are checks every 24 months. The items included in each check and the total routine MH required is summarized. (See Annexure table 3)
A-Checks are relatively easy to plan, however, because the third group of OOP tasks that comes due every 400FH is small. The actual interval of the A check is also likely to be close to 400FH. These OOP tasks can therefore either be scheduled in one of the 'routine' checks at a 100FH interval, or in the A checks if the actual interval is less than 400FH. The APU-related tasks, however, also come due in A checks or a 'routine' check that comes due in multiples of 100FH. The amount of routine labor for A checks is 50-186MH, depending on the size of the check. The group 1 base check tasks come due every 3,000FH and use about 1MH. These can therefore be scheduled either every fifth or sixth A check, or in a 'routine' check. The other main group of base check tasks that are scheduled with A or line checks are the 12- and sometimes 36- month calendar tasks. The 12-month tasks use about 20MH, and can be scheduled with every fourth or fifth A check. The 36-month tasks will add another 7MH when added once every 15-17 A checks. These tasks therefore increase the range of routine labor for most A checks to 50-130MH.
Air Canada follows extensive procedure for Maintenance, Repair and Overhaul (MRO), http://www.aircanada.com/en/about/career/maintenance clearly states that maintenance program has been divided into various subsections like Line Maintenance, Sheet metal and plumbing, Avionics, and lot more, thus dividing program into various activities and costing is to be done on activity basis.
Inputs:
Aircraft-Commerce, Maintenance & Engineering, Issue 52, pg. 52, 54 [June/July 2007] states that the total work packages for A checks include routine inspections, the clearing of deferred defects that have arisen during operation, some component changes and some interior cleaning work. This takes the total labor for these checks to 80-200MH, with an average of over 130MH. Labor charged at a generic rate of $70 per MH will take the cost of the labor portion to $5,600-14,000. The cost of materials and consumables with these checks will be $2,000-4,500. Base check work scopes will have similar items to A checks. In addition to routine inspections, base checks will include: non-routine rectifications; clearing any defects left from operation; incorporation of service bulletins (SBs) and airworthiness directives (ADs); additional OOP tasks;
The non-routine ratio starts off at about 50% of routine MH for young aircraft up to three years old. The MH required for non-routine rectifications therefore increase the labor used. In the analysis and check planning used, the sub-total for routine and non-routine labor starts at about 500MH for the 24-month check, rising to 1,100MH for the 48-month check. The first additional item to be considered is the clearing of deferred defects. The MH required for this is variable, and is 40-200 for base checks. An average of 100MH can be budgeted for base checks. Component changes are the second item. A landing gear ship set, for example, uses about 50MH for removal and reinstallation. Components removed will be hard-timed units, plus on-condition rotables that have failed or require removal. An average of 50MH should be used for this element of the check. An average of 100MH per base check should be used. These additional items therefore add 300-550 MH to the main portions of routine and non-routine labor for the checks. This takes the total for the 24-month check to about 800MH. Most checks are larger, with the 48-month check using 1,500MH.
Reserves:
Labor rates vary, but a generic rate for base maintenance can be used to illustrate the approximate cost of the checks. A labor rate of $50 per MH results in labor costs of $40,000-55,000 for the smaller base checks, and $75,000- 200,000 for the larger checks. The associated cost of materials and consumables for these checks will be $15,000-100,000, depending on the size of the check. This results in total costs of $55,000 for the 24-month check and 48-month check has a cost of $100,000. These checks occur at intervals of 4,000FH, and reserves can be calculated for each subsequent check over its interval or for the cost of a series of checks over this collective interval. The reserves for the 24-month check are $14 per FH. This amount increases to $25 per FH for the 48-month check. The reserves for all inputs for the first five checks amount to 9,800MH and $200,000 of materials and consumables, taking the total cost to about $700,000.
Heavy components
Heavy components comprise: wheels, tyres and brakes; landing gear; thrust reversers; and the APU. Tyres are not remolded by most operators on the CRJ, and are instead replaced at every removal. Aircraft-Commerce, Aircraft operator's and owner's guide pg. 18-32 [Issue 66, October/November 2009] gives a detailed maintenance background on Heavy components , Rotable components, Engine and internal refurbishment as: Removal intervals are 250-300FC, while new nose tyres are $300-350, and new main tyres are $1,300-1,400. The cost of replacing worn tyres is therefore $19 per FC. Wheels are inspected at tyre removal, and then have an overhaul about every fifth removal. Taking into account the typical costs of wheel inspections and overhauls, the cost of wheel repairs is $8 per FC. Brakes are steel, and have a shop visit about every 2,000FC. Taking typical third-party shop visit costs into account, the cost of brake repairs is $30 per FC. The total cost for wheels and brakes equal to $50 per FH. Typical landing gear exchange and overhaul fees are $180,000. Reserves are equal to $9 per FC. Thrust reversers are maintained on condition, and intervals are variable. Taking 15,000FC as an expected average for a reverser shipset of the appropriate size, the cost per FC is $20.
Internal refurbishment
Interior work must also be taken into consideration. This concerns items such as: carpet cleaning and replacement; seat cover cleaning and replacement; seat cushion replacement; cleaning, refurbishing and servicing panels and many more. Seat cover cleaning and servicing of panels and overhead bins will usually be done every C check. Replacing seat covers and refurbishing these items will usually be done every three or four C checks. Taking these intervals, typical cost of materials and MH inputs into consideration; the overall cost for interior refurbishment will be in the region of $15 per FH. The final element will be stripping and repainting. This will cost in the region of $100,000, and will be performed on average once every five C checks, resulting in a reserve of $5 per FH
Rotable components
Rotable components are assumed to be supplied, repaired and managed under an all-in total support package. This is structured with three main elements: a homebase stock which is leased, a pool stock of remaining components which the operator has access to; and a fixed rate per FH fee to cover the repair, transportation and management of all components. Typical rates for the lease of home base stock are equal to $15 per FH. The fixed fee per FH for pool access and stock financing is about $50 per FH. The third element of repair and management costs is in the region of $120 per FH. The total costs for the three elements are $190 per FH.
Engine maintenance
The CF34-3A1 was the first variant, and powers the CRJ-100. This engine has an installed thrust rating of 8,729lbs thrust. Besides a single-stage fan, the engine has a high pressure compressor (HPC), high pressure turbine (HPT) and low pressure turbine (LPT), and multiple life limited parts (LLPs) within these. Operators may therefore have LLPs with varying life limits in new engines. These will be replaced when modules get fully disassembled, and then replaced with later part numbers compared to the original parts in the engine. Engines therefore generally tend to have LLPs with longer lives as they progress through their productive life. The three fan module LLPs have life limits that are as low as 6,000 engine flight cycles (EFC) for the earliest part numbers, and up to 25,000EFC. The current list price for these parts is $227,120. Therefore Engine maintenance will not be an issue for the first five years. Fan disk will be replaced at the end of third year costing $111,200.
Summary of Costs
Activity
Labor
A-Check
Labor total
Material Consumables
Base Checks
24-month check
48-month check
Heavy Components
Wheels and brakes
Gear exchange and overhaul
Reverser shipset
Internal Refurbishment
Stripping &Painting
Rotable components
Engine Maintenance
Fan disk
Table FH- Flying Hours MH- Man Hours FC-Flying Cycle
Conclusion
CRJ-200's are regional jets and are being extensively used in various locations across the globe, CRJ-200's maintenance is no man's play, it requires extensive study of various complex check task and various limited life components. Organizing such tasks without interrupting schedule and performance essentially need expertise and planning. Maintenance of jetliner is one major cost cutting area if tasks are integrated properly otherwise jetliner will be liability rather than being an asset for the company.
Word Count: 2783
ANNEXURE
Inspection Task Group
Interval Flying hours (FH)
Man Hours (MH) for routine inspection
1A
500
50
2A
1000
80
3A
1500
50
4A
2000
95
5A
2500
80
APU1
300
2
APU2
700
2
APU3
1200
2
APU4
1500
2
APU5
1800
2
APU6
3000
2
Out of Phase tasks
400
3
Table A check tasks for first five years (Aircraft- Commerce) Issue 52 June/July 2007
Inspection task group
Maintenance programme Interval
Man Hours for routine inspection
1C
5000 FH
210
2C
10000 FH
280
Gp1 OOP
3000 FH
1
Gp2 OOP
4000 FH
70
Gp3 OOP
8000 FH
40
12-month calendar
12 months
20
18-month calendar
18 months
1
24-month calendar
24 months
40
36-month calendar
36 months
7
48-month calendar
48 months
240
60--month calendar
60 months
10
Table C check tasks for first five years (Aircraft-commerce Issue 52 June/July 2007
Base check
C check tasks
OOP C check tasks
Calendar tasks
Routine Man hours
24-month
1C
Gp 2
12 &24 month
340
48-month
1C+2C
Gp 2&Gp 3
12,24,48 &60 month
658
Table Vertical Integration (Aircraft-commerce Issue 52 June/July 2007
AIRFRAME_LABOR
ENGINE_LABOR
AIRFRAME_REPAIR
ENGINE_REPAIRS
TOT_DIR_MAINT
QUARTER
1082.8
3383.16
1326.55
6338.18
3
1019.06
3368.86
1319.67
6226.08
2
3202.88
4528.98
3862.66
16982.87
1
3398.37
8238.96
16622.18
2
3918
476
12498
13603
32972
1
2979
94
4283
3890
14848
1
684
22
984
894
3411
1
6
1
20
22
53
1
2891
62
3429
3953
13085
2
667
14
791
912
3018
2
2530.07
8835.14
1
4676
10220
27581
51767
2
4708
10666
21474
45519
1
2629.82
8975.14
53.19
14546.24
1
3963
479
13318
3916
26226
2
960.65
3418.18
2314.53
7262.86
1
8
1
27
8
53
2
643.53
-12.13
824.27
1790.31
1
2000.14
4618.53
3
5034
10865
32201
56954
3
2740.58
10117.42
82.91
17671.72
3
652.2
142.81
1259.02
2431.2
2
3593.14
4754.91
4514.41
18383.52
3
535.48
31.47
1740.94
7277.29
2
2683.82
10464.99
292.71
17218.29
2
2823
162
3406
2597
12225
3
693
40
835
637
2999
3
4298
509
14355
7609
29290
3
709.33
540.9
1522.06
3115.14
3
5
1
18
20
47
3
Table 5 Operating Expenses
Cite This Work
To export a reference to this article please select a referencing stye below:
Related Services
View allDMCA / Removal Request
If you are the original writer of this essay and no longer wish to have your work published on UKEssays.com then please: